Rt. 315 under repair
From The Columbus Dispatch article "Roadwork? R-e-l-a-x" (June 15, 2009):
The Rt. 315 construction work involves bridge repairs, ramp improvements and other work that will affect traffic between Goodale Street and North Broadway. The upgrades will take two years and cost about $24 million. Two-way traffic will be maintained, with northbound traffic using two southbound lanes while the northbound lanes are improved. Next year, southbound traffic will use the northbound lanes.
Certain entrance/exit ramps will be closed, depending on the phase of the project, and alternative routes must be taken.